Bissett Lake Project - As you can see from the attached photos, the bridge has arrived in Dartmouth and will be placed Monday afternoon. This should allow the project to be completed by mid-December. The schedule:
- Bridge placement Nov. 19.
 - Finish bridge connections Nov. 21
 - Complete gravel build up to boardwalk Nov. 24
 - Boardwalk completed Dec 8
 - Final crusher dusting & rolling Dec. 12-14
 
If anyone is interested in watching the placement, viewers on the Colby side will be restricted to kiosk area and the existing Phase I trail for safety reasons. The best view of the placement will be from the Brookview side.